Bellevue Addition Correction Response Review
Bellevue, WA

Setback issue caught and settled before resubmittal.
A single-family residence in Bellevue adding space, under City of Bellevue review.
The first City review returned 49 correction comments across building and land use. The design team redrew the set, and the owner wanted an independent check before the response window closed.
Reviewed the original set in September and walked the owner through the gaps behind the correction letter Reviewed the revised architectural set, site plan and structural sheets together in October Found that the new exterior wall assembly added about 3 inches outboard against a 7 inch side yard margin Confirmed the setback still complied and wrote the site plan note that shows the reviewer the arithmetic
Before the response deadline, the owner had the setback question answered on the site plan, a hard dimension in place of a plus or minus, and the site plan moved to the front of the set.
Jurisdiction
County
King County
Permit type
Residential building permit, addition
Scope
Correction response review, setback and site plan review, drawing coordination review
SASHKOV status
Completed
Project stage
Corrections
Engaged
Documents delivered