Seattle Backyard Office Correction Cycle to Issuance
Seattle, WA
IN PROGRESS

Correction cycle next, with all consultants under one contract.
The same northwest Seattle lot, with steep slope relief granted for the office at its application location and a Potential Slide Area designation covering the whole parcel.
Closing five reviewers' corrections means a geotechnical report under Director's Rule 5-2016, structural design from its recommendations, a recorded landslide area covenant, permit history for existing structures and a current site plan, while keeping the owners' total cost in view.
Engaging the selected geotechnical, structural and survey consultants under SASHKOV's contract Scoping the geotechnical report to what the engineer requires for a small structure on a shallow foundation Carrying the engineer's recommendations into structural design and the revised set Preparing the landslide area covenant, the existing structures history and the existing conditions site plan Responding to every reviewer and staying the point of contact with SDCI through issuance
Next phase, starting now that the owners have elected to proceed. The shared timeline targets permit issuance in early 2027 with construction to follow in spring.
Jurisdiction
County
King County
Permit type
SDCI construction permit, detached accessory structure
Scope
Correction response, consultant coordination, permit set revision, permit issuance
Coordinated with
Licensed geotechnical engineer, structural engineer and land surveyor
SASHKOV status
In Progress
Project stage
Corrections