How to Respond to Plan Review Corrections in Shoreline, WA

Shoreline gives 90 days to answer an incomplete notice or a request for more information, and the application is void after that. Answer the first letter completely.

Researched and maintained by SASHKOV · Last verified

2026-11-14

JURISDICTION BREAKDOWN

LAST VERIFIED

2026-11-14

SASHKOV CAN ALSO

Read every comment, coordinate the consultants, revise the set and resubmit one complete response through eTRAKiT inside the 90-day window.

Shoreline runs permits through its eTRAKiT online permitting system. A contractor account lets you see review items and download documents. Most of the time on a Shoreline permit is spent after the first correction letter.

The clocks

  • 90 days to respond. After a notice that the application is incomplete or a request for more information, the applicant has 90 days to provide it (SMC 20.30.110). If not, the application is null and void.

  • Extensions. The Director can grant 90-day extensions when the request is in writing before the deadline and the delay was beyond the applicant's control.

  • Clock paused. The City's review time limit does not run while it waits on your corrections.

  • 180 days of inactivity. A complete application with no substantial steps toward approval for 180 days also expires, with one 180-day extension possible.

Where the time goes

The City's average turnaround table for 2023 applications shows the gap between the first letter and approval:

  • Single-family addition or remodel: 8 weeks to the first correction letter, 18 weeks to approval.

  • New single-family home: 10 weeks to the first letter, 28 weeks to approval.

  • ADU: 11 weeks to the first letter, 23 weeks to approval.

  • Commercial tenant improvement: 9 weeks to the first letter, 15 weeks to approval.

The City notes these are not guarantees and that each extra review adds time. A complete first response is the part the applicant controls.

Common questions

How long do I have to answer a Shoreline correction letter?

90 days from the incomplete notice or request for more information, under SMC 20.30.110. Extensions must be requested in writing before the deadline.

What happens if I miss the Shoreline deadline?

The application is deemed null and void, and the project starts over with a new application.

How long does a Shoreline residential permit take?

The City's 2023 averages show about 18 weeks to approval for single-family additions and remodels and about 28 weeks for new homes.

How SASHKOV handles it

  • Reads every correction comment and builds one item list across all review disciplines.

  • Coordinates structural, civil, energy and survey items with the licensed consultants under one SASHKOV contract.

  • Revises the set so every item is resolved on the drawings, with a response that names the sheet and detail for each comment.

  • Resubmits one complete package through the jurisdiction's portal and tracks each review to issuance, in business days.

Where a building requires a licensed architect or engineer of record, SASHKOV brings them into the contract.

Deadline coming up? See Corrections and Permit Recovery and the City of Shoreline permit page.

Have a correction letter open now? Send the letter and permit number, and SASHKOV will scope the response and the timeline in business days.

Sources

Guides are general information researched from each jurisdiction’s published sources on the date shown. Fees and rules change; confirm with the permitting authority before you act.

Have a site, a permit or a notice? Send it over.

Where SASHKOV’s projects take shape across
Oregon & Washington

Where SASHKOV’s projects take
shape across Oregon & Washington

OREGON

Portland Metro

Multnomah County:

Beaverton

Hillsboro

Tigard

Banks

Unincorporated Washington County

Milwaukie

Oak Grove

Estacada

Rhododendron Unincorporated Clackamas County

Willamette Valley

Lane County:

Eugene

Oregon Coast

Tillamook County:

Tillamook

Bay City

Central Oregon

Deschutes County:

Bend

OREGON

WASHINGTON

Puget Sound

Southwest Washington

Vancouver

Brush Prairie

Yacolt

Unincorporated Clark County

WASHINGTON

© 2026 SASHKOV GROUP LLC dba SASHKOV. All Rights Reserved.

© 2026 SASHKOV GROUP LLC dba SASHKOV.

All Rights Reserved.

UEI TENDYXDNE578 · CAGE 26WF7

NAICS 541611 · 541340 · 541618 · 541990

UEI TENDYXDNE578 · CAGE 26WF7

NAICS 541611 · 541340 · 541618 · 541990

Insured: General Liability & Professional Liability (E&O)

Insured:

General Liability &

Professional Liability (E&O)