PERMIT GUIDE

How to Respond to Plan Review Corrections in Tigard, OR

Tigard takes building permit applications only through its Community Development Hub and asks applicants to plan for longer response times. A complete first response is the best protection against delay.

Researched and maintained by SASHKOV · Last verified

2026-11-12

JURISDICTION BREAKDOWN

LAST VERIFIED

2026-11-12

SASHKOV CAN ALSO

Read every comment, coordinate the consultants, revise the set and resubmit one complete response through the Community Development Hub.

Tigard's Building Division takes building permit applications through the Community Development Hub only; the City no longer accepts them by email or at the counter. It also asks applicants to plan for longer response times because of demand. When review time is long, each extra round costs more.

Settle the address first

A project that needs a new or changed address or suite number needs an Address Application, and the new address must be active in the City's system before a building permit application is accepted. On ADUs, conversions and tenant spaces, this is a common reason a resubmittal sits.

How to answer corrections

  1. Pull every comment from the Hub into one list.

  2. Sort by discipline: building, structural, energy, engineering, planning.

  3. Fix each item on the drawings, not only in the response.

  4. Write one response that names the sheet and detail for each comment.

  5. Resubmit everything at once, with revised calculations and reports included.

Common gaps

Garage conversions and basement work tend to collect comments on fire separation, egress windows, ceiling height and the energy code all at once. Decks and accessory structures are covered by the City's own construction guides; check them before answering a comment about exemptions. The model building codes treat an application as abandoned 180 days after filing unless it is being pursued in good faith, and allow the building official to extend it (IBC and IRC Section 105.3.2). Confirm the local rule and the date on your file before you assume there is time left.

Common questions

How do I submit corrections in Tigard?

Through the Community Development Hub. Tigard no longer accepts building permit applications by email or at the permit counter.

Why is my Tigard application not accepted?

One common reason is the address. A new or changed address or suite number must be active in the City's system before a building permit application is accepted.

How SASHKOV handles it

  • Reads every correction comment and builds one item list across all review disciplines.

  • Coordinates structural, civil, energy and survey items with the licensed consultants under one SASHKOV contract.

  • Revises the set so every item is resolved on the drawings, with a response that names the sheet and detail for each comment.

  • Resubmits one complete package through the City's portal and tracks each review to issuance, in business days.

Where a building requires a licensed architect or engineer of record, SASHKOV brings them into the contract.

Stuck in a correction cycle? See Corrections and Permit Recovery and the City of Tigard permit page.

Have corrections open now? Send the comments and permit number, and SASHKOV will scope the response and the timeline in business days.

Sources

Guides are general information researched from each jurisdiction’s published sources on the date shown. Fees and rules change; confirm with the permitting authority before you act.

Have a site, a permit or a notice? Send it over.

Where SASHKOV’s projects take shape across
Oregon & Washington

Where SASHKOV’s projects take
shape across Oregon & Washington

OREGON

Portland Metro

Multnomah County:

Beaverton

Hillsboro

Tigard

Banks

Unincorporated Washington County

Milwaukie

Oak Grove

Estacada

Rhododendron Unincorporated Clackamas County

Willamette Valley

Lane County:

Eugene

Oregon Coast

Tillamook County:

Tillamook

Bay City

Central Oregon

Deschutes County:

Bend

OREGON

WASHINGTON

Puget Sound

Southwest Washington

Vancouver

Brush Prairie

Yacolt

Unincorporated Clark County

WASHINGTON

© 2026 SASHKOV GROUP LLC dba SASHKOV. All Rights Reserved.

© 2026 SASHKOV GROUP LLC dba SASHKOV.

All Rights Reserved.

UEI TENDYXDNE578 · CAGE 26WF7

NAICS 541611 · 541340 · 541618 · 541990

UEI TENDYXDNE578 · CAGE 26WF7

NAICS 541611 · 541340 · 541618 · 541990

Insured: General Liability & Professional Liability (E&O)

Insured:

General Liability &

Professional Liability (E&O)