Seattle Rooftop Equipment Support Permit Recovery
Seattle, WA

Stalled SDCI correction cycle carried through to completion.
A building in south central Seattle with a mechanical equipment support structure and open trellis over an existing roof deck.
The SDCI review sat in its second correction cycle on one structural comment: the City needed a framing plan and anchorage details showing how the new posts connect to the existing parapet. The original designer was no longer on the project.
Reviewed the drawing set and the full SDCI permit history Coordinated a Washington-licensed structural engineer for a stamped framing plan and parapet anchorage detail, limited to the support structure Incorporated the stamped detail into a revised structure sheet Wrote the response letter and resubmitted through the SDCI portal Stayed on as the reviewer's point of contact through issuance
Took over a stalled second correction cycle and carried the file, the engineer and the City correspondence through to completion under one contract.
Jurisdiction
County
King County
Permit type
SDCI construction permit, rooftop structure
Scope
Permit takeover, correction response, consultant coordination
Coordinated with
Washington-licensed structural engineer
SASHKOV status
Completed
Project stage
Complete