A Stop-Work Order: What to Do in the First Two Business Days

The first days after a stop-work order decide whether it lasts weeks or months. Stop, read the notice, document the site and start the permit path before anything else moves.

A stop-work order lands on a site and the instinct is to call around, argue or keep a few things moving. The projects that recover fastest do the opposite: they stop completely, read exactly what the notice says, and start the paper trail the inspector will want to see.

Day one

  • Stop all work covered by the order. Continuing can add penalties and turn a permit problem into an enforcement case.

  • Read the notice closely. Note the code sections, the scope it covers and any deadline or required action.

  • Secure the site. Make it safe, weather protect open work and keep the posted notice in place.

  • Document everything. Photos, measurements and a list of work done, before anything is covered or removed.

Day two

  • Pull the record. Permit history for the property and any existing permits for the work.

  • Call the inspector or code officer named on the notice. Confirm what they need to lift the order and by when.

  • Decide the path. A permit for unpermitted work, a revision to an existing permit, or removal of the work.

  • Line up the people. Drawings, and an engineer if structure is involved.

What usually lifts the order

A complete permit application or revision that covers the work, and inspections of what was built. Jurisdictions generally treat unpermitted work as new work, so the drawings show the work as built and any changes needed to meet code.

Frequently Asked Questions

Can I keep working after a stop-work order?

Not on the work the order covers. Continuing can add penalties and lengthen the case.

How do I get a stop-work order lifted?

Usually by filing the permit or revision the work needs and passing the required inspections. Confirm the specific requirements with the inspector named on the notice.

Should I document the work before talking to the city?

Yes. Photos and measurements made before anything is covered are the basis for the as-built drawings the permit will need.

Sources

Insights are general information researched from published sources on the date shown. Rules change, so confirm with the permitting authority before you act.

Facing a similar project?

Where SASHKOV’s projects take shape across
Oregon & Washington

Where SASHKOV’s projects take
shape across Oregon & Washington

OREGON

Portland Metro

Multnomah County:

Beaverton

Hillsboro

Banks

Unincorporated Washington County

Milwaukie

Oak Grove

Estacada

Rhododendron Unincorporated Clackamas County

Willamette Valley

Lane County:

Eugene

Oregon Coast

Tillamook County:

Tillamook

Bay City

Central Oregon

Deschutes County:

Bend

OREGON

WASHINGTON

Puget Sound

Lake Stevens

Edmonds

Unincorporated Snohomish County

Southwest Washington

Brush Prairie

Yacolt

Unincorporated Clark County

WASHINGTON

© 2026 SASHKOV GROUP LLC dba SASHKOV. All Rights Reserved.

© 2026 SASHKOV GROUP LLC dba SASHKOV.

All Rights Reserved.

UEI TENDYXDNE578 · CAGE 26WF7

NAICS 541611 · 541340 · 541618 · 541990

UEI TENDYXDNE578 · CAGE 26WF7

NAICS 541611 · 541340 · 541618 · 541990

Insured: General Liability & Professional Liability (E&O)

Insured:

General Liability &

Professional Liability (E&O)