JURISDICTION

City of Beaverton, OR

Beaverton's Community Development Department issues building, planning (land use) and site development permits as separate permit types. The Building Division reviews building, plumbing, mechanical and electrical permits and construction plans and inspects construction for compliance with state and international building codes. The Planning Division reviews development applications against the Beaverton Development Code, and the Site Development Division reviews sewer and sidewalk repairs, street cuts, tree removals and plantings under the city's Engineering Design Manual and City Code. BEPS is used to create a profile, apply for permits, look up applications, request inspections and pay fees.

Researched and maintained by SASHKOV · Last verified

2026-11-02

QUICK ANSWER

Permitting authority: Community Development Department, Building Division. Online submittals: Beaverton Electronic Permitting System (BEPS). Requirements by permit type, review steps and SASHKOV's tips are below.

Permitting authority: Community Development Department, Building Division. Online submittals: Beaverton Electronic Permitting System (BEPS). Requirements by permit type, review steps and SASHKOV's tips are below.

Common application types

  • Building Permit
  • Plumbing Permit
  • Mechanical Permit
  • Electrical Permit
  • Planning (Land Use) Application
  • Site Development Permit
  • Temporary Use Permit

New homes and additions

New single-detached dwellings and middle housing, and floor area additions to them, in the RMA, RMB, RMC and CM-RM zones go through Single-Detached and Middle Housing Design Review One (Development Code Section 40.21), a Type 1 procedure decided by the Director, instead of general Design Review. Construction of a detached garage, and garage, parking or circulation changes that widen frontage along a street, are also Design Review One thresholds. A building permit is reviewed separately by the Building Division.

ADUs and middle housing

An ADU is allowed where a detached dwelling is the principal use in a zone that allows ADUs, and requires an Accessory Dwelling Unit application processed as a Type 1 procedure decided by the Director under Development Code Section 40.05. The city's middle housing amendments to comply with HB 2001 were adopted June 21, 2022 and took effect June 30, 2022. New duplexes, triplexes, quadplexes and townhouses in the MR and CM-MR zones, or in commercial and multiple-use zones where permitted, are reviewed through Design Review Two. A Housing Adjustment (Type 1) allows limited changes to setbacks, lot standards and height for new construction, including middle housing, that meets a minimum density of 17 units per net acre.

Land use review

Each Development Code application is assigned a procedure type that sets the decision maker: Type 1 (Section 50.35) and Type 2 (Section 50.40) applications are decided by the Director, and Type 3 (Section 50.45) applications such as Major Adjustments, new Conditional Uses and Planned Unit Developments are decided by the Planning Commission. Design Review Two and Three submittals must include any information identified through a Pre-Application Conference, and the Facilities Review Committee reviews Single-Detached and Middle Housing Design Review Two and Three applications.

Tips from SASHKOV

  • Planning, site development and building are separate permit tracks, so confirm which ones a project needs before applying.
  • The city accepts electronic PDF submissions for land use applications, site development permits and building permits.
  • Check the zone first: single-detached and middle housing in RMA, RMB, RMC and CM-RM use Section 40.21 design review rather than general Design Review.

Where to apply

Permitting authority: Community Development Department, Building Division. Online submittals: Beaverton Electronic Permitting System (BEPS).

On your own or with SASHKOV

ON YOUR OWN

WITH SASHKOV

Find the rules

Read the code, zoning and checklists yourself

Researched and confirmed for your site

Prepare documents

Draw the set, or hire each consultant separately

Permit set prepared, with licensed consultants under one contract

Corrections

Answer each reviewer comment yourself

Responses prepared and resubmitted

Deadlines

Track intake, expirations and inspections

Tracked in business days from intake to issuance

Sources

Breakdowns are general information researched against the jurisdiction’s published sources on the date shown. Requirements change; confirm with the permitting authority before you commit to a design or a purchase.

Projects here

Projects here

No published projects here yet. SASHKOV works with this jurisdiction; start a project to talk through yours.

Starting a project here?

Where SASHKOV’s projects take shape across
Oregon & Washington

Where SASHKOV’s projects take
shape across Oregon & Washington

OREGON

Portland Metro

Multnomah County:

Beaverton

Hillsboro

Banks

Unincorporated Washington County

Milwaukie

Oak Grove

Estacada

Rhododendron Unincorporated Clackamas County

Milwaukie

Oak Grove

Estacada

Rhododendron

Unincorporated Clackamas County

Willamette Valley

Lane County:

Eugene

Oregon Coast

Tillamook County:

Tillamook

Bay City

Central Oregon

Deschutes County:

Bend

WASHINGTON

Puget Sound

Lake Stevens

Edmonds

Unincorporated Snohomish County

Southwest Washington

Brush Prairie

Yacolt

Unincorporated Clark County

© 2026 SASHKOV GROUP LLC dba SASHKOV. All Rights Reserved.

© 2026 SASHKOV GROUP LLC dba SASHKOV.

All Rights Reserved.

UEI TENDYXDNE578 · CAGE 26WF7

NAICS 541611 · 541340 · 541618 · 541990

UEI TENDYXDNE578 · CAGE 26WF7

NAICS 541611 · 541340 · 541618 · 541990

Insured: General Liability & Professional Liability (E&O)

Insured:

General Liability &

Professional Liability (E&O)