PERMIT GUIDE
Stop-Work Orders and Unpermitted Work in Seattle
An SDCI stop work order takes effect when posted, and you have 2 business days to request a review. Work done without a permit is legalized through a permit plus a special investigation fee.
Researched and maintained by SASHKOV · Last verified
2026-11-07
JURISDICTION BREAKDOWN
LAST VERIFIED
2026-11-07
SASHKOV CAN ALSO
Record existing conditions before covered work is opened, prepare the permit set for the work as built, coordinate the structural engineer, and answer corrections through to final inspection.
What the order means
SDCI issues a stop work order when work is contrary to the code or a permit, or when site conditions are unsafe (Seattle Building Code 103.3; Seattle Residential Code R103.3). It takes effect when posted at the site, names the violation and may stop all work on the site. SDCI can also stop work for unpaid fees; work then resumes only with the Director's written authorization.
Deadlines
Request a review in writing within 2 business days of service.
SDCI holds the review within 2 business days of the request and decides within 2 business days after it. The order can be withdrawn or modified.
A Notice of Violation usually gives 30 to 60 days to correct. A citation brings an immediate fine with no correction period.
What it costs
Work started without a permit carries a special investigation fee on top of the permit fee (2026 Fee Subtitle, SMC 22.900B.020). It is not refundable.
Value of work up to $5,000: $292
$5,001 to $50,000: $876
$50,001 to $100,000: $1,460
$100,001 to $500,000: $2,920
$500,001 to $5 million: $14,600
Over $5 million: 100% of the permit fee
Civil penalties under the building codes can reach $500 per day per violation, and violating a stop work order can lead to criminal charges.
Legalizing the work
Unpermitted construction is permitted like new work, plus the investigation fee. Framing cannot be covered without inspection approval, so expect to open finishes where the inspector asks; the City does not pay to remove material for inspection.
A use that was legal when it began but never permitted can be recognized through a Construction Permit – Establishing Use. It needs 2 pieces of documentation showing the use existed before the critical date, such as tax records, utility records or signed statements. Initial review takes 2 to 3 weeks for simple applications and 8 weeks for complex ones. Applications go through the Seattle Services Portal.
How SASHKOV handles it
Reads the notice and sets the response dates in business days.
Records existing conditions and prepares the as-built drawings.
Brings in the structural engineer or other licensed professional the work needs, under one contract.
Prepares the permit application, answers corrections and coordinates inspections through issuance.
More on SDCI: the City of Seattle breakdown.
Sources
Guides are general information researched from each jurisdiction’s published sources on the date shown. Fees and rules change; confirm with the permitting authority before you act.
Have a site, a permit or a notice? Send it over.
OREGON
Portland Metro
Multnomah County:
Beaverton
Hillsboro
Banks
Unincorporated Washington County
Willamette Valley
Lane County:
Eugene
Oregon Coast
Tillamook County:
Tillamook
Bay City
Central Oregon
Deschutes County:
Bend
WASHINGTON
Puget Sound
Southwest Washington
Brush Prairie
Yacolt
Unincorporated Clark County